Replacing commercial HVAC: what to do before you buy

A rooftop unit, boiler or chiller is sized to the load the building puts on it. Cut the load first and the new equipment is smaller, cheaper and runs better. NRCan's retrofit guidelines put heating and cooling replacement last for that reason.

An auditor walking between rooftop heating and cooling units on a snowy commercial roof

The order NRCan recommends

Equipment comes last
StageWhat it covers
1. Existing building commissioningFind out how the building runs now and fix what is set wrong: schedules, setpoints, sensors and controls.
2. LightingLighting changes the heat the building gives off, so it changes both the heating and the cooling load.
3. Other loadsEquipment, plug loads and the building envelope. Each cut here is load the new plant never has to meet.
4. Air distributionFans, ducts and ventilation rates, matched to the loads that are left.
5. Heating and coolingOnly now size and replace the boilers, chillers and rooftop units, to the smaller load.

The order is from NRCan's Major Energy Retrofit Guidelines for commercial and institutional buildings: each stage changes the loads the next one has to serve. By its figures a minor retrofit saves up to 15% of a building's energy use and a major one 15 to 40%.

Where you are now

Pick your case
Your situationStart withWhy
Equipment is near the end of its life and a replacement is in the capital planA Level 2 auditIt sizes the loads and prices the options together, and it is the level most incentives and loans accept. The three levels.
Comfort complaints or rising bills, with equipment in mid-lifeRecommissioningNRCan puts the saving at 5 to 15% with a payback of less than 3 years in most cases, without new equipment.
A unit has failed and must be replaced nowA load check on that unitNRCan notes many systems are oversized to begin with. Check before copying the old nameplate, then plan the rest.
A switch of fuel, or a building under a reporting or performance ruleA Level 3 analysisCapital-intensive changes need detailed cost and savings analysis. 8 mandatory reporting rules are in force in the places we cover. Reporting rules.

What heating equipment is sized to, city by city

70 cities

Heating plant is sized to the design temperature: the cold the building has to handle in all but the coldest hours of a normal winter. In the 70 cities we cover it runs from −1°C in Saanich to −39°C in Yellowknife, which is why a design copied from another city, or from the unit being replaced, can be wrong for the building.

CityDesign heating temperatureHeating degree days
Vancouver, BC −4°C 2,768
Calgary, AB −26°C 4,876
Saskatoon, SK −33°C 5,695
Winnipeg, MB −31°C 5,542
Toronto, ON −16°C 3,559
Montréal, QC −22°C 4,028
Moncton, NB −22°C 4,514
Halifax, NS −16°C 3,870
Charlottetown, PE −19°C 4,404
St. John's, NL −13°C 4,578
Whitehorse, YT −36°C 6,522
Yellowknife, NT −39°C 7,856

The largest city we cover in each province and territory. Every city, with its utilities, rules and incentives.

Incentives that pay for the study

33 open programs

Of the programs we track, 33 are open and pay toward audits, engineering studies or recommissioning: the work that comes before the purchase. 6 of them pay for recommissioning or building optimisation:

Check each program's rules on approval before work starts and on the audit level it accepts. Every incentive we track, by province.

Ask every supplier

  1. What load is this sized to?Ask for the calculation, not the nameplate of the unit being replaced.
  2. What changes if we cut the load first?A smaller unit costs less to buy and runs closer to its best efficiency.
  3. How does it perform at part load?Most hours of the year are mild. Ask for efficiency at typical conditions, not only at full output.
  4. How will it be controlled?Who programs the schedules, setpoints and outdoor-air settings, and how it ties into the building automation system.
  5. Who commissions it?Ask for functional testing at handover and a report you keep.
  6. Which refrigerant, and what does service cost?Ask what the maintenance contract covers and what the warranty requires.
  7. Which incentive applies, and when must we apply?Ask before anything is ordered: many programs need approval first.

Common questions

Should we replace commercial HVAC like for like?

Usually not without checking. NRCan's retrofit guidelines note that many existing systems are oversized to begin with, and that a planned replacement is the opportunity to right-size. A system sized to the building's real load costs less to buy and runs more efficiently at typical conditions.

What does recommissioning save?

NRCan puts the saving at 5 to 15% of energy use, with a payback of less than 3 years in most cases, and notes it can sometimes reach 30%. It also shows how the building actually runs, which is what the new equipment should be sized to.

Do we need an energy audit before replacing HVAC?

For a planned replacement, yes. An ASHRAE Level 2 audit covers the loads, the operating changes and the capital options together, and it is the level most incentives and retrofit loans ask for. A major capital project usually needs the detailed analysis of Level 3.

A unit has failed. Is there time for any of this?

Not for all of it, but there is time to check the size against the load, ask for the controls and commissioning to be included, and ask whether an incentive applies before the order is placed. Then plan the rest of the building's equipment properly, before the next failure.

Planning a replacement?

Tell us the building and the equipment in question. We'll help you scope the audit that should come first.